Submitting a planning application can be a complex and, at times, stressful experience for applicants and developers. Having confidence that an application is going to be considered in a reasonable way is at the heart of what applicants seek from local planning authorities.


Where a party acts in an unreasonable way, a Planning Inspector can award costs against them during a planning appeal. This can either be a full award of costs, which means the party's whole costs for the appeal process must be paid, or a partial award.


Viable Placemaking frequently support with the submission of planning applications and appeals. Where possible, we endeavour to work with all stakeholders, including a Local Planning Authority, in a positive and pragmatic way to achieve a positive decision.


In some cases, planning applications are refused which we believe should be approved. This does not mean the Council have acted unreasonably. However, on some occasions, we believe that a party has not behaved in a reasonable way. For a Local authority, examples of unreasonable behaviour include:


  • Lack of co-operation with the other party

  • Preventing or delaying development which should clearly be permitted

  • Refusing planning permission on a planning ground capable of being dealt with by conditions

  • Imposing a condition that is not necessary, relevant to planning and to the development to be permitted, enforceable, precise and reasonable in all other respects.


Of course, there is also a risk of costs being awarded against an appeallant. For example, if an applicant fails to cooperate or withdraws an appeal without good reason.


In a recent case, Viable Placemaking acheived planning permission for a commercial development subject to condition. While some conditions were discussed with the Case Officer, the LPA's planning committee applied additional conditions which were not necessary or relevant to the development to be permitted.


Viable Placemaking understand that planning committees can come to a different decision to that reccomended by officers, but recognised that the conditions were not necerssary. Therefore, we submitted a Section 73 application to remove these conditions, including those added by the committee members.


Unfortunately, the LPA refused the Section 73 application. Viable Placemaking then submitted a planning appeal which included an application for costs. The Planning Inspector awarded costs for the time taken to submit the appeal relating to the conditions added by the committee, as these were clearly unnecessary and to uphold them was unreasonable.


Viable Placemaking do not submit an application for costs with every planning appeal we submit on a decision we disagree with. However, when we do, it is where we believe a party has been unreasonable.